Wednesday 12 September 2012

We have a slab!!!

Our slab was poured this morning after the footings were done yesterday. We are very happy to be one day ahead of schedule already!!

Please head over to the 'Slab' album to view the photos from yesterday and today. I am hoping to get some better photos tomorrow.

Next on the list is delivery of site shed and toilet some time this week, drains on Monday 17/09 then power and water to slab on Tuesday 18/09. Doors and window frames are also to be delivered on Tuesday 18/09.

Yippee :D