Wednesday 26 September 2012

Bricks!

So Monday saw the delivery of our bricks and the start of the brick laying!! It was so surreal seeing the first wall built today after visiting the block with no change for so long.

Our site supervisor says that brickwork will be done by the end of October and the roof will be on by mid-November!! At this rate we could get our keys by February 2013 *happy dance*

Photos from today have been uploaded to the Brickwork album.

Wednesday 12 September 2012

We have a slab!!!

Our slab was poured this morning after the footings were done yesterday. We are very happy to be one day ahead of schedule already!!

Please head over to the 'Slab' album to view the photos from yesterday and today. I am hoping to get some better photos tomorrow.

Next on the list is delivery of site shed and toilet some time this week, drains on Monday 17/09 then power and water to slab on Tuesday 18/09. Doors and window frames are also to be delivered on Tuesday 18/09.

Yippee :D